← Back to search

Permitted26/AP/1106Submitted 4 months agoChange of use

London Borough of Southwark

Details of Condition 2 -Hard and soft landscaping scheme as required by planning permission 25/AP/0769 dated 09/03/2026 for Formation of 'Community Charging' EV recharging facility on existing private residential car park (change of use from car park ancillary to residential (C3) to commercial EV charging station (sui generis). Development to comprise the installation of 3.no rapid chargers to serve 6.no new EV charging bays, together with ancillary electrical equipment including substation. Removal of boundary palisade fencing replacement with new hooped barriers along boundary. New pole mounted lights. New surface treatment.

Find on council portal

Tracking, tags and letters are part of the paid plan. See what it costs. Searching and reading any record stays free.

Progress

Submitted
20 Apr 2026
— completed
Validated
20 Apr 2026
— completed
Consultation
— completed
Target date
14 Jun 2026
— completed
Decided
20 May 2026
— completed

Application details

Reference
26/AP/1106
Local authority
Southwark
Ward
RYLA
Application type
All Other
Property type
Commercial

Key dates

Submitted
20 Apr 2026
Validated
20 Apr 2026
Target decision
14 Jun 2026
Decided
20 May 2026

Estimated project value

£15k–£100k

Typical UK cost for this job type, at UK average rates (2026). Estimated from the proposal description — planning applications do not state build cost. Source: trade estimate.

Planning constraints

No designations recorded at this location. This is not a formal search — always confirm with the local authority before relying on it.

Designations from planning.data.gov.uk, Open Government Licence v3.0. Indicative only — not a formal local authority search.