Permitted26/AP/0501Submitted 6 months agoDriveway

London Borough of Southwark

Details of Condition 5 'Arboricultural Method Statement' required by planning permission ref no. 23/AP/3273 'Refurbishment of South Dock Marina boatyard to include demolition and removal of all buildings and structures on site, renew services infrastructure, new electricity substation, underground drainage, and hard standings and provide new workshops, studios, toilets showers laundry and associated landscape. Construct new covered boat repair areas with associated gantry and staircase. Removal of the existing crane and replace with new crane, pontoon adjacent to the crane and associated public realm works to the crane area. Addition of new trees to the river walk'.

Find on council portal

Tracking, tags and letters are part of the paid plan. See what it costs. Searching and reading any record stays free.

Map of the site

Progress

Submitted
19 Feb 2026
— completed
Validated
19 Feb 2026
— completed
Consultation
— completed
Target date
15 Apr 2026
— completed
Decided
25 Feb 2026
— completed

Application details

Reference
26/AP/0501
Local authority
Southwark
Ward
SUDO
Application type
All Other
Property type
House

Key dates

Submitted
19 Feb 2026
Validated
19 Feb 2026
Target decision
15 Apr 2026
Decided
25 Feb 2026

Estimated project value

£3k–£10k

Typical UK cost for this job type, at UK average rates (2026). Estimated from the proposal description — planning applications do not state build cost. Source: MyJobQuote 2026, £40-£120/m² installed.

Planning constraints

No designations recorded at this location. This is not a formal search — always confirm with the local authority before relying on it.

Designations from planning.data.gov.uk, Open Government Licence v3.0. Indicative only — not a formal local authority search.