PermittedS23/0323Submitted 3 years agoSolar

Land To The North Of The A1 (Foston Bypass) Foston Grantham

Submission of details reserved by conditions 4 (construction method statement) and 5 (archaeological WSI) for S20/1433 (Installation of a solar farm comprising ground mounted solar PV panels with a generating capacity of up to 49.9MW, including mounting system, battery storage units, inverters, underground cabling, stock proof fence, CCTV, internal tracks and associated infrastructure, landscaping and environmental enhancements for a temporary period of 40 years and a permanent grid connection hub.)

View on council portalDocuments (10)

Tracking, tags and letters are part of the paid plan. See what it costs. Searching and reading any record stays free.

Map of the site

Progress

Submitted
14 Feb 2023
— completed
Validated
14 Feb 2023
— completed
Consultation
14 Apr 2023
— completed
Target date
11 Apr 2023
— completed
Decided
20 Jun 2023
— completed

Application details

Reference
S23/0323
Local authority
South Kesteven
Ward
Viking Ward
Application type
Conditions
Property type
Agricultural

Key dates

Submitted
14 Feb 2023
Validated
14 Feb 2023
Target decision
11 Apr 2023
Decided
20 Jun 2023

10 documents · 0 comments · 0 constraints

Estimated project value

£5k–£10k

Typical UK cost for this job type, at UK average rates (2026). Estimated from the proposal description — planning applications do not state build cost. Source: trade estimate.

Planning constraints

No designations recorded at this location. This is not a formal search — always confirm with the local authority before relying on it.

Designations from planning.data.gov.uk, Open Government Licence v3.0. Indicative only — not a formal local authority search.

Nearby applications