Hinkley Point C Connection Project, Between Bridgwater In Somerset And Seabank Substation, North Of Avonmouth

Formal submission to discharge Requirement 17 (Drainage Management Plan) and Requirement 20 (Watercourse Protection Plan) for Stage 2.1 of the authorised development) of the National Grid (Hinkley Point C Connection Project) Order 2016 (as Amended)

View on council portalDocumentsComment

Tracking, tags and letters are part of the paid plan. See what it costs. Searching and reading any record stays free.

Progress

Submitted
13 Nov 2026
— completed
Validated
13 Nov 2026
— completed
Consultation
—
— not yet reached
Target date
18 Dec 2026 (target)
— not yet reached
Decided
—
— not yet reached

Application details

Reference
26/P/2328/DCO
Local authority
North Somerset

Key dates

Submitted
13 Nov 2026
Validated
13 Nov 2026
Target decision
18 Dec 2026

Planning constraints

No designations recorded at this location. This is not a formal search — always confirm with the local authority before relying on it.