Permitted2020/3325Submitted 5 years agoBoundary treatment

231 - 237 GRAHAM ROAD Hackney

Creation of new southern access to Hackney Central Overground Station from Graham Road and creation of associated facilities /structures including a shelter with ticket gates, a kiosk, bike storage, a new staff refuge area and landscaping. *Please note that due to the Cyber Attack on Hackney Council's IT systems, any comments made under the previous application will not be considered and should be resubmitted under this application reference.*

Tracking, tags and letters are part of the paid plan. See what it costs. Searching and reading any record stays free.

Map of the site

Progress

Submitted
4 Nov 2020
— completed
Validated
4 Nov 2020
— completed
Consultation
26 Nov 2020
— completed
Target date
30 Dec 2020
— completed
Decided
15 Jul 2021
— completed

Application details

Reference
2020/3325
Local authority
Hackney
Ward
Hackney Central Ward
Application type
All Other

Key dates

Submitted
4 Nov 2020
Validated
4 Nov 2020
Comments close
26 Nov 2020
Target decision
30 Dec 2020
Decided
15 Jul 2021

Estimated project value

£2k–£10k

Typical UK cost for this job type, at UK average rates (2026). Estimated from the proposal description — planning applications do not state build cost. Source: trade estimate.

Planning constraints

No designations recorded at this location. This is not a formal search — always confirm with the local authority before relying on it.

Designations from planning.data.gov.uk, Open Government Licence v3.0. Indicative only — not a formal local authority search.

Nearby applications