PermittedDC/25/0087/DRCSubmitted over a year agoBoundary treatment

Parcel Of Land Within Norwich Road Industrial Estate West Of Halesworth Business Centre Norwich Road Halesworth Suffolk

Discharge of Condition No. 3 of DC/23/4213/VOC - Variation of Condition 2 of DC/21/0521/FUL - (Development of a 50MW battery storage facility with associated infrastructure) - Amend to UKPN and Customer 132kV Compound, 11kV Substation, Metering Enclosure and DNO Cables, Battery Units, Fencing and Gate(s), Lighting Column Points, Access Track, Private 33kV Switch Room, Private Control Room, Auxiliary Transformer - Written Scheme of Noise Mitigation

View on council portalDocuments (6)

Tracking, tags and letters are part of the paid plan. See what it costs. Searching and reading any record stays free.

Map of the site

Progress

Submitted
9 Jan 2025
— completed
Validated
9 Jan 2025
— completed
Consultation
—
— completed
Target date
6 Mar 2025
— completed
Decided
13 Mar 2025
— completed

Application details

Reference
DC/25/0087/DRC
Local authority
East Suffolk
Ward
Halesworth And Blything
Application type
Conditions

Key dates

Submitted
9 Jan 2025
Validated
9 Jan 2025
Target decision
6 Mar 2025
Decided
13 Mar 2025

6 documents · 1 comments · 0 constraints

Estimated project value

£2k–£10k

Typical UK cost for this job type, at UK average rates (2026). Estimated from the proposal description — planning applications do not state build cost. Source: trade estimate.

Planning constraints

No designations recorded at this location. This is not a formal search — always confirm with the local authority before relying on it.

Designations from planning.data.gov.uk, Open Government Licence v3.0. Indicative only — not a formal local authority search.

Nearby applications