Woodland North Of Bank Top Wood And Mytholmroyd Canal Wharfe Blackstone Edge Road Cragg Vale Hebden Bridge Calderdale

Carry out a programme of essential improvement works to a section of our existing 11kV overhead electricity network. The scheme involves rebuilding sections of the existing overhead line and replacing poles that have reached the end of their serviceable life - Mytholmroyd Canal Wharfe

View on council portalDocuments (2)Comment

Tracking, tags and letters are part of the paid plan. See what it costs. Searching and reading any record stays free.

Progress

Submitted
4 Nov 2026
— completed
Validated
4 Nov 2026
— completed
Consultation
—
— not yet reached
Target date
16 Dec 2026 (target)
— not yet reached
Decided
—
— not yet reached

Application details

Reference
26/90036/ELC
Local authority
Calderdale
Ward
Luddendenfoot
Application type
Outline

Key dates

Submitted
4 Nov 2026
Validated
4 Nov 2026
Target decision
16 Dec 2026

2 documents · 0 comments · 24 constraints

Planning constraints

No designations recorded at this location. This is not a formal search — always confirm with the local authority before relying on it.

Designations from planning.data.gov.uk, Open Government Licence v3.0. Indicative only — not a formal local authority search.