Pending105:EPF/1887/26Submitted 2 weeks ago

Waltham Cross to Tottenham Substation, near to Highbridge Street, Waltham Abbey

Application to discharge requirement 3 – Written scheme setting out all stages of the authorised development (SW 3 C) by National Grid Electricity Transmission plc for an Order Granting Development Consent for the North London Reinforcement Project for the uprating of an existing 275kV transmission line of approximately 14km in length from Waltham Cross substation to Tottenham substation to enable it to run at a voltage of 400kV, together with associated development (Revised application to EPF/2072/25, EPF/0226/25 & EPF/0277/26).

Tracking, tags and letters are part of the paid plan. See what it costs. Searching and reading any record stays free.

Progress

Submitted
8 Oct 2026
— completed
Validated
8 Oct 2026
— completed
Consultation
—
— not yet reached
Target date
—
— not yet reached
Decided
—
— not yet reached

Application details

Reference
105:EPF/1887/26
Local authority
Epping Forest

Key dates

Submitted
8 Oct 2026
Validated
8 Oct 2026

Planning constraints

No designations recorded at this location. This is not a formal search — always confirm with the local authority before relying on it.

Designations from planning.data.gov.uk, Open Government Licence v3.0. Indicative only — not a formal local authority search.